Waste Coal Mine Gas Power Station Design Philosophy
Envirogen has chosen to use individual containerised 1
MW and 3 MW reciprocating gas engine generator sets for its waste coal mine gas
power stations, to allow maximum efficiency and flexibility. Using this
proven technology ensures that generation can be undertaken over a broad
range of gas qualities at different mine sites while also enabling cost
effective maintenance programs and operational efficiencies.
Gas Engines The current operational power stations use 1 MW
and 3 MW, Austrian built, GE Jenbacher
reciprocating engines.
The generators are individually enclosed in
locally fabricated steel containers complete with noise baffling and
fireproofing. The engine enclosures have been custom designed to suit
specific site requirements including cooling and ventilation, to ensure
that there is no derating at high ambient air temperatures. Each
container is fitted with its own carbon dioxide deluge fire fighting
system and noise abatement measures are also incorporated to meet
stringent Environmental Planning Authority conditions.
Gas Handling
Systems Gas filters, blowers and pipework have been designed
specifically for each power station based on gas specifications for that
site. Gas filtration has been designed to ensure that particles as small
as 5 microns are filtered out, with easy cleaning of the filter system
that minimise down time. Blower type and sizing and gas pipework are
designed to ensure a moderate level of redundancy whilst ensuring that
capital cost and auxiliary electrical loads are minimised.
Electrical High voltage transformers are inherently reliable and the power station
design consequently has one generator unit step up transformer shared
between two generating units. This is considered an effective balance
between cost and risk of failure. These unit transformers step up the
generator voltage from 415V to 11kV. An indoor 11kV busbar arrangement
then links all generator sets to a common busbar. The export voltage of
33kV or 66kV is then achieved by way of a single step up station
transformer.
Fully Computerised Control Rooms A fully automated and
computerised control room operates all power station plants
automatically, 24 hours per day, 7 days per week. It includes automatic
control of the gas engines, gas delivery pressures and quantities,
blower control, System Control and Data Acquisition System (SCADA) for
analyzing and reporting power station performance and alarms either
locally or remotely. The stations are managed throughout normal business
hours with staff on call and remotely linked to the stations SCADA
system for any out of hour requirements.
|